What does an owner's representative cost?

Fee models, AHO rates, counter-calculation · Reading time 9 minutes

Short answerIn 50 words

What an owner's representative costs, in brief

As a full mandate, an owner's representative costs a mid single-digit percentage of eligible cost, degressive with project size. The fee table of AHO booklet no. 9 (6th edition, May 2025) gives 3.3 percent for project control at 15 million and around 2 percent at 50 million euros; project leadership is remunerated separately by time.

Below 15 million euros the 6th-edition table contains no values; there the fee is calculated by time under section 5. The 5th-edition table (2020) gave four to six percent for such schemes in zone III. There is no binding fee scale; owner's representation is not a service under the HOAI.

The rate alone says little. It depends on the scope, on the complexity of the scheme and on what it refers to. And it can only be judged against what it prevents: awards without competition, change orders waved through, extended construction periods and defects after acceptance.

Fee modelsThree routes

Percentage, fixed fee or time

No.ModelHow it works · When it fits
01Percentage of construction costA rate on the eligible cost, under section 6 of the AHO booklet cost groups 200 to 700 of DIN 276 without 711 to 713, excluding VAT. Under the AHO table roughly three to four percent at 15 to 20 million euros and degressive: the larger the volume, the smaller the rate. Below 15 million the 5th-edition table (2020) gives four to six percent for zone III; the 6th edition calculates by time there. Fits full mandates across all phases. Important: fix the reference base, otherwise the fee rises with the very costs it is meant to reduce.
02Fixed fee per phaseA fixed amount per project stage, calculated from scope and effort. Fits clearly delimited phases, such as procurement and construction, and owners who want certainty in the fee. Changes of scope are renegotiated.
03Time-based feeHourly or daily rates with a budget cap. Fits single tasks: review of a general contractor agreement before signature, support during a procurement, taking over a project in difficulty, early-stage advice.
DriversWhat the rate depends on

What the rate depends on

Scope. A full mandate across project preparation, design, procurement, construction and close-out sits at the upper end; individual phases sit proportionally below. The AHO booklet no. 9 spreads the fee across five project stages: 19 percent project preparation, 21 percent design, 22 percent construction preparation, 30 percent construction, 8 percent close-out. The largest share falls on construction, because that is where change orders, schedule and quality have to be checked continuously.

Project size. The rate is degressive. Control effort does not grow linearly with construction volume: a residential scheme with 40 units does not need four times as many meetings as one with ten. Small schemes therefore sit at five to seven percent under the 5th-edition table, large ones at around two under the 6th.

Complexity. The AHO booklet no. 9 distinguishes project classes by difficulty; three of five carry table values. A refurbishment under continued operation, a special building with a full permit procedure or a scheme with many stakeholders sits higher than a new build on a clear site.

Duration. Since the sixth edition of May 2025, the table values are for the first time linked to reference values for project duration. If a project drags on, the control effort rises without construction cost rising. That is why percentages alone fall short on long projects.

AHO fee table6th edition, May 2025

What the table gives for project control

Eligible costFee, class IIIShare
15 million €495,189 €3.3 percent of eligible cost, reference duration 30 months.
20 million €600,336 €3.0 percent, duration 33 months.
30 million €773,835 €2.6 percent, duration 36 months.
50 million €1,023,747 €2.05 percent, duration 42 months.
100 million €1,833,663 €1.8 percent, duration 51 months.
250 million €3,929,324 €1.6 percent, duration 63 months.

The table applies to the basic services of project control in project classes II to IV; class II sits roughly a fifth below, class IV about 15 percent above. The project class follows from six assessment areas scored one to five each, client organisation, project structure, stakeholder environment, quality, cost and schedule targets; the average is the class. The bidder scores, the client checks. One of the six areas is the client organisation: a developer with an in-house project department lowers the project class and with it the fee; in class I the fee is calculated by time anyway. Intermediate values are interpolated linearly. Below 15 million euros the table no longer contains values since the sixth edition; there the fee is calculated by time. The 5th-edition table (2020) still ran from 0.5 to 500 million euros and shows how the curve runs below that, zone III in each case: 4.1 to 4.8 percent at 5 million, 4.9 to 5.9 percent at 2 million, 5.6 to 6.7 percent at one million. The 6th-edition values sit in the middle of those ranges.

Project leadership is not included. Where the owner additionally assigns project leadership tasks, the AHO booklet has them remunerated separately by time. The charge rate for a project manager is 18,000 to 23,000 euros per month or 1,000 to 1,300 euros per day, as of the first quarter of 2025. A flat five percent for expenses comes on top. Owner's representation with authority is exactly this combination of control and leadership.

The booklet provides two corrections. For work on existing buildings a surcharge on the basic fee applies, to be agreed in text form; absent an agreement, 20 percent applies where the task is at least of average difficulty. Where a general contractor, general planner or design-and-build contractor is used, the project control fee falls, but only moderately: to 87 to 89 percent of the basic fee with a general contractor or general planner, to 66 percent with a design-and-build contractor after project development. Control does not disappear, it shifts.

Below 15 millionTime instead of table

How it works for smaller schemes

For project classes I and V, AHO booklet no. 9 refers to time-based remuneration (section 5); for schemes below 15 million euros the table contains no values, so in practice the fee is calculated under section 5 as well. Two forms are provided: a settlement fee based on hours actually performed and documented, and a fixed fee based on a staffing plan estimated in advance. Under section 4 the fixed fee remains unchanged even if the effort later turns out differently; if the client changes the project requirements, the additional or reduced effort is settled separately.

The section describes the process in four steps:

No.Step under section 5What the booklet provides
01Framework conditionsA settlement fee on documented time units or a fixed fee from estimated staffing (section 5 para. 1). The fixed fee should only be agreed once the project framework is sufficiently clear; on more complex projects, settlement on actual effort is expedient in the initial phase to gauge future capacity needs (section 5 para. 2 c and d).
02Schedule frame and staffing planThe fixed fee is derived from a schedule frame and a specific staffing plan per project (section 5 para. 3): around ten framework activities or milestones, including the project stages and their durations, with staffing by role per activity. This yields person-months (chapter 7.1.1).
03Rates and expensesPerson-months times charge rate; where work is not continuous over a month, daily or hourly rates apply (section 5 para. 2 a). Plus a flat five percent for expenses (section 7). There is no refurbishment surcharge under time-based fees, unlike under the table (section 5 para. 2 b).
04Changes and durationThe fixed fee remains unchanged even if the effort turns out differently (section 4 para. 6). If the client changes the requirements, the effort actually performed and documented counts, unless the additional effort is the contractor's responsibility (section 5 para. 2 e). If the duration extends, an adjustment is to be examined (section 4 para. 8).

The charge rates of section 5 para. 2, excluding VAT and expenses; unless agreed otherwise the mid-points apply. They refer to actual deployment time on the project, absences are not charged, and besides staff cost they include the contribution to management, secretariat and office overheads:

FunctionMonthDay · per hour at eight hours
PMProject manager18,000 to 23,000 € per month · 1,000 to 1,300 € per day, roughly 125 to 160 € per hour.
Sen.Senior project engineer15,000 to 18,000 € per month · 800 to 1,000 € per day, roughly 100 to 125 € per hour.
Jun.Junior project engineer13,000 to 15,000 € per month · 700 to 800 € per day, roughly 90 to 100 € per hour.
Ass.Project assistant9,000 to 11,000 € per month · 500 to 600 € per day, roughly 60 to 75 € per hour.

This is how it works under the AHO commentary and in practice: the firm sets up a schedule frame with around ten framework activities or milestones, including the project stages with their durations, and enters the staffing per activity by role: leader of project control, project engineer, project assistant. This yields person-months; multiplied by the charge rates, it produces the fixed fee per project stage. For comparability the fixed fee is usually also stated as a percentage of construction cost; so project control for schemes between 5 and 15 million euros lands at four to six percent under the 5th-edition table and in our experience, smaller schemes above that; project leadership comes on top. A flat five percent for expenses comes on top. Defined single tasks, such as the review of a general contractor agreement, are charged by time with a budget cap. An instalment plan is agreed (section 8), in practice along the project stages; if the duration extends beyond what was agreed, an adjustment is to be examined (section 4 para. 8).

A staffing plan for a residential scheme with 8 million euros of construction cost and 24 months' duration could look like this, using the mid-points of the AHO rates:

No.DeploymentCalculation
01Project management, 40 percent9.6 person-months at 20,500 € = 196,800 €
02Senior project engineer, 30 percent7.2 person-months at 16,500 € = 118,800 €
03Assistant, 10 percent2.4 person-months at 10,500 € = 25,200 €
04Expenses, 5 percenton 340,800 € = 17,040 €
ΣFixed fee357,840 €, roughly 4.5 percent of construction cost

This is a model calculation with disclosed assumptions, not an offer. It shows why percentages rise on smaller schemes: the minimum staffing of a project does not fall in step with construction cost. Whether owner's representation with authority is included decides the share of project management, and with it the largest item.

The AHO booklet calculates its own standard example both ways, a research building with roughly 143.7 million euros of eligible cost and 55 months' duration: 154 person-months yield 2,442,500 euros net, the fee table 2,856,297 euros. Both routes sit at 1.7 to 2.0 percent of eligible cost; the difference is the room for negotiation (chapters 7.1.3 and 7.2).

Counter-calculationWhat the fee prevents

Where the fee comes back

What matters is not the rate but what it prevents. Four levers, each on its own in the order of the fee or above:

Award prices. In our experience a general contractor usually comes in 10 to 15 percent above the sum of separate awards; the premium depends on market conditions and contract maturity and shows reliably only in comparison with the individual bids. Whoever awards separately with control, or has the GC contract reviewed before signature, starts here. We set out the comparison in General contractor or separate trades?

Change orders. A change order is to be examined on merit and amount. Without review it is paid; with review it is negotiated, reduced or rejected. Where the cost arises is shown by a Hertie School study (Kostka and Anzinger, 2015): 119 completed large German projects ended on average 73 percent above the original estimate, with design deficits and lack of control as the main causes. Large public projects cannot be transferred to a private scheme; the direction still holds.

Construction period. Every month of delay costs interim financing, lost rent or a postponed sale, and site overheads. Schedule control is the service that is least visible and saves the most.

Defects. A defect noticed before acceptance is the contractor's problem. One noticed afterwards is a dispute with an open outcome. Preparing acceptance and pursuing defects is therefore no formality but the last place where the fee is earned.

Model calculationAssumptions disclosed

A worked example

Assume a residential scheme with 8 million euros of eligible construction cost and a full mandate of project control and project leadership at five percent: a fee of 400,000 euros over the whole duration. Counter-calculation: a single avoided or reduced change order of five percent of construction cost covers the fee in full. A general contractor premium of ten percent, avoided in whole or in part by separate awards with control, would equal 800,000 euros. One month less construction time equals, at this volume, a five-figure sum in financing and site overhead costs.

This is a model calculation with the ranges given above, not a project result. It shows the ratio, not the outcome: a fee in the single-digit percent range competes against items that are individually larger than the fee itself. As a rule, professional control therefore pays for itself. Whether it does for a specific scheme can be estimated before appointment, and it should be.

ContractFive points

What matters in the fee agreement

No.PointWhy
01ScopeRefer to the AHO booklet no. 9 and name the project stages and action areas commissioned. Without a scope, no fee is comparable.
02Reference baseFor a percentage fee, fix the eligible cost at the cost calculation stage, as section 6 of the AHO booklet provides; until its approval the fixed fee is provisional. Otherwise the representative earns from the cost increases they are meant to prevent.
03AuthorityDefine what the representative may release: payments, change orders up to a limit, design decisions. Everything above stays with the owner.
04IndemnityEvidence the cover on a project basis. The representative is liable for control, review and advice, not for design and execution.
05TerminationTerminable per project stage with settlement of work performed. A full mandate the owner cannot leave is not a good sign.
When Solid EstateThe owner's representative who is an owner

How we disclose the fee

We disclose the ratio of fee to leverage before appointment, and we say so when it does not hold for a scheme. We regularly act as owner ourselves, with our own capital at risk, and therefore know what a change order costs that nobody has examined.

As owner's representation in Munich and Bavaria we offer full mandates, individual phases and single tasks such as the review of a general contractor agreement. What the role covers in detail is set out in What does an owner's representative do?

Frequently asked

What clients ask about this

How are the costs of owner's representation calculated?

Usually as a percentage of eligible cost, under section 6 of the AHO booklet cost groups 200 to 700 of DIN 276 without 711 to 713: the fee table gives 3.3 percent for project control at 15 million euros, degressive for larger schemes; below 15 million by time, with project leadership charged separately by time. Alternatively as a fixed fee per project stage or a time-based fee with a budget cap. The reference base should be fixed at the cost calculation stage.

Is the fee part of the ancillary construction costs?

Yes. Under DIN 276, project management and project control fall into cost group 710, owner's tasks. The fee is therefore part of the ancillary costs and included in a complete cost plan from the start.

What are the hourly rates under the AHO booklet?

AHO booklet no. 9 gives monthly and daily rates, not hourly ones. For project managers it is 1,000 to 1,300 euros per day, roughly 125 to 160 euros per hour, for project engineers 700 to 1,000 euros per day. As of the first quarter of 2025, excluding VAT and expenses; unless agreed otherwise the mid-points apply. Project control firms quote market hourly rates of up to about 200 euros depending on region and task; that is a market figure, not an AHO figure.

How is the fee calculated for schemes below 15 million euros?

By time, either as a settlement fee on documented hours or as a fixed fee from a staffing plan: who is deployed with what share over what duration, multiplied by the AHO charge rates. The fixed fee is usually also stated as a percentage of construction cost; the 5th-edition table gives four to six percent for project control in zone III, more for very small schemes, and project leadership comes on top. There is no refurbishment surcharge under time-based fees (section 5 para. 2 b).

Is there a surcharge for work on existing buildings?

Yes. Under section 6 of AHO booklet no. 9, project control services for existing buildings carry a surcharge on the basic fee, to be agreed in text form and measured by integration, flexibility, risk, complexity and organisation of the works. Absent an agreement, 20 percent applies where the task is at least of average difficulty. Under time-based fees the surcharge does not apply (section 5 para. 2 b).

Does the fee fall when a general contractor is appointed?

Only moderately. AHO booklet no. 9 sets 87 to 89 percent of the basic project control fee where a general contractor or general planner is used, and 66 percent for a design-and-build contractor after project development. The tasks shift from coordinating trades to contract, change orders and schedule; they do not disappear.

Does the HOAI apply to owner's representation?

No. The HOAI governs design services of architects and engineers. Project control and owner's representation are not included. The scope and non-binding fee guidance come from the AHO booklet no. 9.

Is an owner's representative worthwhile for small projects?

Then usually not as a full mandate but for single tasks: reviewing the contract before signature, supporting the procurement, the acceptance. Whether a full mandate pays off is shown by the staffing plan before appointment.

What does the review of a general contractor agreement cost?

It is usually charged by time or as a fixed fee and depends on the size of the specification. Measured against what a single open point in the contract later costs as a change order, it is the cheapest service in the entire project.

Sources: AHO booklet no. 9, Project management in the construction and real estate industry, 6th edition, May 2025, chapter 2 sections 3 to 8 with fee table and charge rates and chapter 7 commentary on fees, figures 7.1 to 7.5 · AHO booklet no. 9, 5th edition, March 2020, fee table figure 2.4 (0.5 to 500 million euros) and section 5 para. 3 · DIN 276:2018-12, cost group 710 · HOAI 2021 · Kostka, G. and Anzinger, N. (2015): Large infrastructure projects in Germany – Between ambition and reality, Hertie School of Governance. Reviewed on 29 September 2026 against AHO booklet no. 9, 6th edition (May 2025). General information, not legal or fee advice for an individual case.

Let's talk about your project

Whether control pays for your scheme can be estimated before appointment. We disclose the calculation, even when it goes against us.

[06] Contact

Get in touch

[Address]Solid Estate GmbH
Hochstraße 7
81669 Munich, Germany

Planning a construction project, looking for a partner for your development, or would you like to learn more about our projects? We look forward to hearing from you.

We use your details solely to process this enquiry. See our privacy policy. Prefer direct contact? info@solidestate.de

Solid Estate